September 28, 2025
2h ago

KETRACO Completes Crucial Power Line to Reduce Blackouts

KETRACO Completes Crucial Power Line to Reduce Blackouts

The new upgrade is set to benefit millions of Kenyans...

✨ Key Highlights

Kenya Electricity Transmission Company Limited (KETRACO) has completed the restoration of a crucial 400kV Double Circuit Transmission Line, a significant step to reduce blackouts in northern Kenya and enhance grid reliability.

  • The project, valued at Ksh46.13 million and USD 1,598,660 (Ksh207 million), involved replacing six collapsed transmission towers near Longonot.
  • The line will facilitate the evacuation of up to 300 MW of wind power from the Lake Turkana Wind Power (LTWP) plant.
  • The restoration of Circuit 1 was completed on September 20, with Circuit 2 scheduled for September 28.
  • This restoration coincided with the appointment of Kipkemoi Kibias as KETRACO’s Acting Managing Director and Chief Executive Officer.