Govt Directed to Terminate Contracts in Ksh 45B Project

The projects, jointly funded by the African Development Bank and the Kenyan government, have faced significant delays, and postponing the creation of thousands of projected jobs...
✨ Key Highlights
Members of Parliament are demanding the termination and blacklisting of contractors responsible for significant delays in the Ksh 45.5 billion Kenya Towns Sustainable Water Supply and Sanitation Programme.
- The programme, funded by the Government of Kenya and the African Development Bank, covers 61 water and sanitation projects across 58 towns.
- The National Assembly's Departmental Committee on Blue Economy, Water and Irrigation issued the directive to the Principal Secretary for Water and Sanitation, Julius Korir.
- Lawmakers cited non-performing contractors, governance issues, court disputes, and escalating costs as reasons for the delays, emphasizing that the public deserves access to essential services.
Continue Reading
Read the complete article from Kenyans
Part of the Day's Coverage
KeNHA Intensifies Talks as Evictions Loom Along Several Nairobi and Machakos Towns - June 2026
The Kenya National Highways Authority (KeNHA) is engaging with traders and local leaders along the Kangundo Road corridor as a 30-day eviction notice for encroaching on road reserves nears its expiry. Members of Parliament are demanding the termination and blacklisting of contractors responsible for significant delays in the Ksh 45.5 billion Kenya Towns Sustainable Water Supply and Sanitation Programme. The Commission on Administrative Justice (CAJ) has also ordered the Tana River County Government to release information on the Inuka Fund and recommended the Acting County Secretary for prosecution over non-compliance with information requests and official summons.