Court halts construction of Sh11.5b railway project, orders fresh tender

Justice Gregory Mutai faulted the government over the project's funding, procurement and implementation...
✨ Key Highlights
The High Court has halted the construction of the Sh11.5 billion Riruta-Ngong Commuter Meter Gauge Railway Project, declaring it unconstitutional due to procedural and financial irregularities.
- The Sh11.5 billion project was halted for violating constitutional provisions regarding funding, procurement, and public participation.
- Key entities involved include President William Ruto's administration, the High Court, and petitioners led by Busia Senator Okiya Omtatah.
- The court ordered a fresh, constitutionally compliant tender process, mandating parliamentary approval and genuine public engagement within 90 days.