Government fails to stop Sh147.77 market construction case

Government fails to stop Sh147.77 market construction case

The government has failed in its bid to stop a Sh147.77 million case over the construction of Economic Stimulus Programme (ESP) Markets within Nakuru County...

✨ Key Highlights

A Kenyan court has dismissed the government's attempt to halt a Sh147.77 million construction case related to Economic Stimulus Programme (ESP) Markets in Nakuru County.

  • The case involves construction company Extreecon Engineering and government entities including the Principal Secretary Housing and Urban Development South Regional, the Attorney General, and Tej Architects.
  • Judge Joseph Sergon ruled that the court's jurisdiction cannot be ousted by an arbitration clause, allowing the case to proceed to full hearing.
  • Extreecon Engineering is seeking to restrain the government from terminating its contract for the construction of ESP Markets, valued at Sh147.77 million.