KETRACO completes Nanyuki-Isiolo electricity transmission line after delays

The 72-kilometre line, which has been under development since 2012, is expected to improve electricity reliability in Nanyuki, Isiolo, Meru, Laikipia and surrounding areas by providing an alternative transmission route and increasing the capacity of the regional grid...
✨ Key Highlights
Kenya Electricity Transmission Company (KETRACO) has successfully energized the 72-kilometer 132kV Nanyuki-Isiolo electricity transmission line, more than a decade after construction began in 2012.
- The project is expected to significantly improve electricity reliability and capacity in the Mt Kenya and Upper Eastern regions, including Nanyuki, Isiolo, Meru, and Laikipia.
- KETRACO, the state-owned electricity transmission company, announced an immediate improvement in voltage levels at the Nanyuki substation post-energization.
- The infrastructure includes a new 132kV substation at Isiolo and an expansion of the existing Nanyuki substation, with a 4.2km section redesigned as an underground cable due to security restrictions near Laikipia Air Base.