KETRACO completes Loiyangalani–Suswa grid restoration

NAIROBI, Kenya, Sept 29 - The Kenya Electricity Transmission Company (KETRACO) has completed restoration of the Loiyangalani–Suswa 400kV double circuit Kenya breaking news | Kenya news today |..
✨ Key Highlights
The Kenya Electricity Transmission Company (KETRACO) has finished restoring the Loiyangalani–Suswa 400kV double circuit transmission line, allowing for full power evacuation from the Lake Turkana Wind Power plant.
- The restoration involved the design, supply, and erection of six new towers near Longonot.
- KETRACO acting MD Kipkemoi Kibias stated that both circuits being energized ensures N-1 contingency, reducing outage risks.
- The project was carried out by Elemech Engineering.