Senator Ledama Issues Updates on Narok Airport Construction After Kenyans Slam Ruto

Ruto initially set March as the completion date for the Maasai Mara International Airport, but he later revised the timeline to the end of the year...
✨ Key Highlights
Narok Senator Ledama Ole Kina has defended President William Ruto against accusations of broken promises regarding the Maasai Mara International Airport construction, stating the project is 60% complete.
- The runway construction is reportedly 60% complete.
- Key individuals involved include Senator Ledama Ole Kina and President William Ruto.
- The Senator attributed delays to the long rains and partially blamed the Narok County Government for the terminal building's progress.